Progress Report on Our Project
15 January 2022

Work has progressed well and the sub-base below the new flooring has been levelled and prepared for the electrical contractor to start on Monday 17th. The new electrical conduits and wiring will be laid in preparation for the electric power and heating installations.

The flooring stone is being cut and prepared in Weldon Stone’s yard.

The photographs below show the sub-base for the stone flooring being prepared. The yellow dust extraction units are in use to reduce the amount of dust in the church.